DID Sarikei Schemes

 

DID Sarikei Schemes


DID SARIKEI DIVISION
ABOUT US HYDROLOGY ORGANISATION CHART
SCHEME FUNCTION CONTACT US
QUOTATION NOTICE

 

BUNDONG SIAN I DRAINAGE SCHEME
 

District Meradong
Project Construction 1998
Date Of Completion 1999
Project Location The Project is located on the right bank of Batang Rajang opposite Bintangor Town

Project Area

400 Ha

Project Cost

RM 1,060,000.00

Project Objectives

The main objective of the project is to prevent sea water Ingression into the Scheme as the area is low laying land and is subjected to flood.

Project Components

- 17.5 KM of Perimeter & Internal Bund and drain.

- 2 nos. Of Tidal Control Gate

- 6 nos. Of Control Drop

- 5 nos. Of Belian Bridges

 

 

BUNDONG SIAN II DRAINAGE SCHEME
 

District Meradong
Project Construction 2000
Date Of Completion 2001
Project Location The Project is located on the right bank of Batang Rajang opposite Bintangor Town

Project Area

800 Ha

Project Cost

RM 1,170,000.00

Project Objectives

The main objective of the project is to prevent sea water Ingression into the Scheme as the area is low laying land and is subjected to flood.

Project Components

- 18 KM of Perimeter & Internal Bund and Drain.

- 3 nos. Of Tidal Control Gate

- 1 no. Of Control Drop

- 3 nos. Of Belian Bridges

- 9 nos. Of creek closure

 

 

 

Copyright © Department Of Irrigation & Drainage Sarawak


Last Updated On 19 Dec 2024

Operating Hours

Monday - Thursday
8:00am to 1:00pm & 2:00pm to 5:00pm
Friday
8:00am to 11:45pm & 2:15pm to 5:00pm
Saturday, Sunday & Public Holiday
Counter closed

image Polls
image Announcement