BUNDONG SIAN I DRAINAGE SCHEME |
|
| District | Meradong |
| Project Construction | 1998 |
| Date Of Completion | 1999 |
| Project Location | The Project is located on the right bank of Batang Rajang opposite Bintangor Town |
|
Project Area |
400 Ha |
|
Project Cost |
RM 1,060,000.00 |
|
Project Objectives |
The main objective of the project is to prevent sea water Ingression into the Scheme as the area is low laying land and is subjected to flood. |
|
Project Components |
- 17.5 KM of Perimeter & Internal Bund and drain. - 2 nos. Of Tidal Control Gate - 6 nos. Of Control Drop - 5 nos. Of Belian Bridges |
|
BUNDONG SIAN II DRAINAGE SCHEME |
|
| District | Meradong |
| Project Construction | 2000 |
| Date Of Completion | 2001 |
| Project Location | The Project is located on the right bank of Batang Rajang opposite Bintangor Town |
|
Project Area |
800 Ha |
|
Project Cost |
RM 1,170,000.00 |
|
Project Objectives |
The main objective of the project is to prevent sea water Ingression into the Scheme as the area is low laying land and is subjected to flood. |
|
Project Components |
- 18 KM of Perimeter & Internal Bund and Drain. - 3 nos. Of Tidal Control Gate - 1 no. Of Control Drop - 3 nos. Of Belian Bridges - 9 nos. Of creek closure |