RIVER BASIN AND COASTAL ZONE MANAGEMENT DIVISION
ABOUT US OGANISATION CHART  PROJECTS WORK FLOW
CONTACT PERSON
 

 

COASTAL EROSION CONTROL PROTECTION WORKS
NO. PROJECT LOCATION
YEAR OF
COMPLETION
LENGTH / TYPE OF PROTECTION WORKS
MALAYSIAN
PLAN
FUND
1 Sg. Serpan, Asajaya, Samarahan
1994
300m - Rock Revetment 6 MP Federal
2 Pantai Bintulu Phase I, Bintulu
1994
300m & 60m   - Groyne 6 MP Federal
3 Sg. Bilis, Asajaya, Samarahan 1995 350m - Rock Revetment 6 MP Federal
4 Km 2 Miri-Kuala Baram Road, Miri 1997 650m - Rock Revetment 7 MP Federal
5 Damai Golf Course, Kuching 1997 500m-Rock Revetment
State
6 Pantai Bintulu Phase II, Bintulu
1998
Two 60m - Rock Revetment
150m - Rock Revetment
7 MP Federal
7 Marine Dept. Lighthouse, Kuala baram, Miri
1998 200m - Rock revetment
State
8 Kpg. Teluk Nipah, Buntal, Kuching
1999 1.8km - Rock Revetment 7 MP Federal
9 Km 9, Jln. Miri-Kuala Baram, Miri
1999 374m - Rock Revetment
State
10 Pantai Lutong, Jln. Miri-Kuala Baram, Miri
2000 470m Rock Revetment 7 MP Federal
11 Holiday Inn Damai Lagoon Resort, Kuching
2001 380m Rock Revetment
90m - Stepped revetment

State
12 Taman Seaview, Bintulu
2001
178m - Rock Revetment
8 MP
Federal
13 Km20 Jln. Miri-Kuala baram, Miri
2001 1.5km - Rock revetment
8 MP
Federal
14 Marine Dept. Lighthouse, Kuala Baram, Miri
2002 Rock revetment
State
15 Pantai Kpg. Punang, Lawas, Limbang
2004 500m - Rock Revetment
8 MP
Federal
16 Pantai Kpg. Pasir Pandak, Kuching
2005
400m - Rock Revetment
8 MP
Federal
17 Pantai Taman Good Park, Bintulu
2005
100m - Rock Revetment
8 MP
Federal
18 Kampung Tanah Hitam, Sematan, Kuching
2005 180m - Rock Dumping
8 MP
Federal
19 Kampung Batu Satu, Lutong, Miri
2005 180m - Rock Dumping
8 MP
Federal
20 Kpg. Rejang, Mukah 2006 580m - Rock Revetment
9 MP
Federal
21 Sg. Serpan, Asajaya, Samarahan
2006 400m - Rock revetment
9 MP
Federal
22 Jln. Miri-Kuala Baram (Pan Borneo Highway), Miri
2006 1.9km - Rock Revetment
9 MP
Federal
23 Kpg. Santubong, Kuching
2007 390m - Rock Revetment 9 MP Federal
24 Pantai Kpg. Punang (Phase II), Lawas, Limbang
2007 200m - Rock Revetment 9 MP Federal
25 Marriot Resort & SPA, Miri
2007 550m - Rock Revetment
170m - Rock Revetment
9 MP Federal
26 Pantai Ria, Bintulu 2008 - 9 MP Federal
27 Kampung Buntal Lama
2008 168m - Rock Revetment
9 MP
Federal
28 Menaiktaraf Struktur Kawalan Hakisan Pantai di Kpg. Santubong, Kuching 2008 JPS Concrete Block
9 MP
Federal
29 Lot 854, Jln. Dk Tem. Oyong Lawai, Miri 2008 -
9 MP
Federal
30 Jabatan Kesihatan, Miri 2008 -
9 MP
Federal
31 Mariott Resort & SPA, Miri 2008 -
9 MP
Federal
32 Kpg. Batu Satu, Jln Kuala Baram, Miri 2008 -
9 MP
Federal
33 Kampung Bejaya, Miri 2008 -
9 MP
Federal
34 Beach Park, Bintulu 2008 -
9 MP
Federal
35 Tg. Bungai, Miri 2008 -
9 MP
Federal
36 Km 22 Jln. Lutong-Kuala Baram, Miri 2008 -
9 MP
Federal
37 Jln. Miri-Kuala Baram (Pan Borneo Highway) Phase II, Miri
2009 800m - Rock Revetment
9 MP
Federal
38 Kpg. Tanah Hitam, Sematan (Phase II), Kuching 2009 Rock Revetment
9 MP
Federal
39 Kampung Litong, Mukah
2009 425m - JPS Concrete Block
9 MP
Federal
40 Kampung Pasir Pandak Phase II, Kuching 2010 Rock Revetment
9 MP
Federal
41 Jln Lutong-Kuala Baram (Phase III), Miri 2010 -
9 MP
Federal
42 Pejabat Kastam Sematan, Kuching 2010 -
9 MP
Federal
43 Kampung Buntal Lama (Phase II), Kuching 2010 Rock Revetment
9 MP
Federal
44 Kampung Pasir Panjang, Kuching 2010 500m -'Terrafix or Interlocking Concrete Block
9 MP
Federal
45 Jln. Lutong-Kuala Baram (Phase IV), Miri 2010 Rock revetment
9 MP
State
46 Water Front Santubong, Kuching 2012 150m - Rock Revetment with 350m pedestian walkway, 3 nos. staircase & 5 nos. concrete bench
9 MP
Federal
47 Sg. Bangat, Lawas 2012 Rock Revetment 10 MP State
48 Muara Sg. Tekuyung, Kuching 2012

-construction of 76m earth bund
-construction of 146mx0.9m concrete drain
- construction of 1 nos. of 0.9m box culvert c/w HDPE flag gate.

10 MP State
49 Rehabilitation Sg. Tekuyung River Mouth Erosion Protection Structures 2013 - 10 MP State